eFundi Upgrade to 11.4

Project Description

The request was initiated by Adelle Lotter on 01 Aug 2017

01 Aug 2017: The project is approved, but the following should be noted:

  1. RISK: The upgrade is in parallel with the Restructuring system changes scheduled for Dec 2017.  This should be listed on the IT Risk Register
  2. COMMUNICATION: The communication to the system owners should include information on the risk.  February is also part of the risk-timeframe (due to registrations)

 

 

Documents

Project Progress

100%

Project Timing

  • Start
    Aug 31 2017
  • End
    Dec 11 2017

08/31/2017 12/11/2017

100%

Overall Project Completion

  • 20%
  • 60%

100%

  • 40%
  • 80%

1. Sakai OOTB implementation Complete 100% Tasks 3 / 3

100%
Description

 

3 of 3 completedTasks

  • Create Git repository
  • Add Sakai OOTB code to Master branch
  • Test Git Repo with Ansible play

2. Add NWU Changes and Integrations Complete 100% Tasks 9 / 9

100%
Description

 

9 of 9 completedTasks

  • CAS
  • Skin
  • Dev Database upgrade
  • Lesson changes
  • Test Resources
  • Test Announcement
  • Test Assignments
  • Tracs
  • eVission

3. Course Management changes Complete 100% Tasks 3 / 3

100%
Description

 

3 of 3 completedTasks

  • Course link integration with course offering web service
  • Course management integration with Consolidation / sAPI
  • Ini integration with Consolidation

4. Inegrations Complete 100% Tasks 5 / 5

100%
Description

 

5 of 5 completedTasks

  • Turnitin
  • Big blue button
  • Scorm
  • Blog
  • Opencast

5. Test environment Complete 100% Tasks 5 / 5

100%
Description

 

5 of 5 completedTasks

  • Test Database upgrade
  • Test all functionalities
  • Stress testing
  • Create git production 2017 branch
  • Test Ansible play

6. Production upgrade Complete 100% Tasks 1 / 1

100%
Description

 

1 of 1 completedTasks

  • Test production functionalities

Project Discussion 2 Responses to eFundi Upgrade to 11.4

  1. The NWU changes for upgrading to 11.4 needs to be finished by the end of October

    October 19, 2017 at 10:52 am
    CIELLIE JANSEN VAN VUUREN
  2. Downloaded repo Will test and create working git repo next week

    September 22, 2017 at 3:25 pm
    CIELLIE JANSEN VAN VUUREN