HPC Upgrade Project

Project Description

The request was initiated by Riaan Marx on 30 April 2019

Situation/Problem/Opportunity (WHAT):

A)    Our current HPC (high performance computing) OS software install is a bit behind the CHPC (Centre for high performance computing). There were a request from our users to get the current HPC system in line with CHPC for ease of transition back and forth between the two environments.

Documents

Project Progress

50%

Project Timing

  • Start
    May 01 2019
  • End
    Mar 04 2021

05/01/2019 03/04/2021

76%

Overall Project Completion

  • 20%
  • 60%

50%

  • 40%
  • 80%

1. Build test Env Complete 100% Tasks 1 / 1

100%
Description

Done

2. Build Prod Complete 0% Tasks 0 / 1

0%
Description

0 of 1 completedTasks

  • Provision Prod

Project Discussion 9 Responses to HPC Upgrade Project

  1. Projek staan nou eers still, ander projekte het eers voorkeur gekry oor die projek gesamentlik met onvoorsiene omstandighede.

    August 18, 2020 at 9:49 am
    JACQUES OOSTHUIZEN
  2. Ek vra Jacques om te update. Ander prioriteite het die projek laat stilstaan tot groot mate.

    August 18, 2020 at 9:43 am
    RIAAN MARX
  3. Ciellie en Martin Dryer het al die persone wat op die ou sandpit was oor geskuif na die nuwe toets omgewing en is nou besig om getoets te word.

    February 24, 2020 at 10:00 am
    JACQUES OOSTHUIZEN
  4. Het Jacques gevra om vir ons te update

    February 24, 2020 at 8:59 am
    RIAAN MARX
  5. Jacques sal vir ons update hier.

    January 22, 2020 at 2:35 pm
    RIAAN MARX
  6. Jacques will follow up with Ciellie

    September 10, 2019 at 8:45 am
    RIAAN MARX
  7. We are still waiting for confirmation that Test is ok and we may continue with prod.

    September 10, 2019 at 8:44 am
    RIAAN MARX
  8. 21 May 2019: The request was approved by the PMB

    May 21, 2019 at 11:58 am
    YVETTE LABUSCHAGNE
  9. New Rocks 7.x Test Env build and operational

    May 20, 2019 at 11:53 am
    RIAAN MARX

Leave a Reply