Implementation of the Devman system (BSS)

Project Description

Request was initiated by Mari Prinsloo

1) Devman (Kidz) die offisiele stelsel vir NWU sal wees vir die hantering van community projekte, fundraising, event management en Alumni. Die Stakeholder Databasis wat afsonderlik ontwikkel is sal uitfasseer en oorskuif na DEVMAN. Daar is egter bepaalde leemtes wat in die opgradering van DEVMAN tot institusionele stelsel aangespreek moet word waar onder:
* Ontwikkeling en implementering van Community engagement
* opgradering van die Integrasie tussen sentrale stelsels en DEVMAN
* uitrol van Kommunikasie module om Stakeholder DB te vervang
* opgradering en uitrol van fundraising management sodat rekordhouding van fundrasing kan plaasvind
* uitrol van Alumni en Konvokasie sodat STakeholder DB kan verval
* potensieel uitrol van event management

Befonding vir Community engagement is verkry vanaf Bibi Boumand – R78 000
Befondsing uit IA is verkry en versprei oor 2 y vir die res van die ontwikkeling
Lisensie uitbreiding in BSS se begroting vir 2016 reeds goedgekeur

Projekleier: Paul Grober

Documents

Project Progress

100%

Project Timing

  • Start
    Mar 01 2015
  • End
    Dec 31 2017

03/01/2015 12/31/2017

100%

Overall Project Completion

  • Community Engagement

    20%
  • Development & Fundraising

    60%

100%

  • 40%

    Integration

  • 80%

    Communication & Marketing

20%

Community Engagement

40%

Integration

60%

Development & Fundraising

80%

Communication & Marketing

1. Community Engagement Complete 100% Tasks 4 / 4

100%
Description

4 of 4 completedTasks

  • Business Analysis
  • Development
  • Testing
  • Implementation

2. Integration Complete 100% Tasks 4 / 4

100%
Description

4 of 4 completedTasks

  • Analysis
  • Development
  • Testing
  • Implementation

3. Development & Fundraising Complete 100% Tasks 4 / 4

100%
Description

4 of 4 completedTasks

  • Analysis
  • Development
  • Testing
  • Implementation

4. Communication and Marketing Complete 100% Tasks 4 / 4

100%
Description

4 of 4 completedTasks

  • Analysis
  • Development
  • Testing
  • Implementation

5. Data Migration Complete 34% Tasks 1 / 3

34%
Description

1 of 3 completedTasks

  • Analysis
  • Migration testing
  • Migration