IT Infrastructure Projects (FIDC)

Project Description

List of all the active FIDC projects where OI Infrastructure is involved with.

4/9/2019

Mafikeng Campus = 7

Potchefstroom Campus = 8

Vaal Triangle Campus  = 6

Total Projects = 25

Documents

No documents at this time.

Project Progress

21%

Overall Project Completion

  • 20%
  • 60%

21%

  • 40%
  • 80%

1. MFK: A5 CLB FIDC006/2018MC Complete 95% Tasks 9 / 10

95%
Description

Upgrading of lecture halls in A5 CLB building

Phase 1 of project: 4 Lecture Halls 18 July 2019

  •  24 Network Points
  •  12 Wi-Fi AP’s
  •  0 IP Telephone

Phase 2 of Project: 5 Lecture Halls 30 November 2019

  • 48 Network Points
  • 14 Wi-Fi AP’s
  • 0 IP Telephone

9 of 10 completedTasks

  • Phase 1: Estimates & Quotations
  • Phase 1: Site handover for project
  • Phase 1: Installation
  • Phase 1: Practical completion
  • Phase 1: Project works completion
  • Phase 2: Estimates & Quotations
  • Phase 2: Site handover for project
  • Phase 2: Installation
  • Phase 2: Practical completion
  • Phase 2: Project works completion

2. MFK: A2 New Labs FIDC008/2018MC Complete 100% Tasks 5 / 5

100%
Description

Upgrading of PC labs in building A2

  • 245 Network Points
  • 11 Wi-Fi AP’s
  • 12 IP Telephones

May 2019

5 of 5 completedTasks

  • Estimates & Quotations
  • Site handover for project
  • Installation
  • Practical completion
  • Project works completion

3. MFK: A7 Upgrade basement of Library FIDC007/2019MC Complete 20% Tasks 1 / 5

20%
Description

Macro Maintenance of basement and labs in the Library of Mafikeng.

  • 199 Network Points
  • 13 Wi-Fi AP’s
  • 16 Telephones

February 2020

 

*04/09/2019. still waitning for tender commitee

1 of 5 completedTasks

  • Estimates & Quotations
  • Site handover for project
  • Installation
  • Practical completion
  • Project works completion

4. MFK: B5 MBADA Residences FIDC008/2019MC Complete 24% Tasks 1 / 5

24%
Description

Macro Upgrading of MBADA residences at Mafikeng

  •  198 Network Points
  •  88 Wi-Fi AP’s
  •  0 Telephones

site hand over 11 July 2019

Practical completion of all 22 units 7 may 2020

 

1 of 5 completedTasks

  • Estimates & Quotations
  • Site handover for project
  • Installation
  • Practical completion
  • Project works completion

5. MFK: A17 New Building for Psychosocial Health FIDC0032019MC Complete 20% Tasks 1 / 5

20%
Description

New Building for Psychosocial Health

  •  198 Network Points
  •  88 Wi-Fi AP’s
  •  0 Telephones

Site hand over 7 Aug  2019

Practical completion  To be determined

 

1 of 5 completedTasks

  • Estimates & Quotations
  • Site handover for project
  • Installation
  • Practical completion
  • Project works completion

6. MFK:C1 Fleet vehicles and wash bay Complete 18% Tasks 0 / 5

18%
Description

Constructing  space for Fleet vehicles and wash bay

    •  3 Network Points
    •  0 Wi-Fi AP’s
    •  1 Telephones

 

Site hand over 19 Sept 2019

Practical completion To be determined

0 of 5 completedTasks

  • Estimates & Quotations
  • Site handover for project
  • Installation
  • Practical completion
  • Project works completion

7. MFK: New Student Housing (1728 beds) on the Mafikeng Campus Complete 13% Tasks 1 / 8

13%
Description

New Student Housing (1728 beds) on the Mafikeng Campus

Phase 1: 1-3 blocks of the units including Water reservoir

  • 993 Network points
  • 9 IP Telephones
  • 111 WiFi Aps

Phase 2 :4-6 Blocks of units including Sub station,and new gate

  • 993 Network points
  • 13 IP Telephones
  • 112 WiFi Aps

Site hand over phase 1 ————2019

Practical completion phase 1 ———–2020

Site hand over phase 2———–2020

Practical completion Phase 2 ———2021

 

1 of 8 completedTasks

  • Estimates & Quotations Phase 1 and 2
  • Site handover for project phase 1
  • Installation
  • Practical completion
  • Site handover for project Phase 2
  • Installation
  • Practical completion
  • Project works completion

8. MFK:Relocate Protection Services FIDC009/2019MC Complete 20% Tasks 1 / 5

20%
Description

Relocate Mafikeng Campus Protection Services to New Space

 

  •  26 Network Points
  •  3 Wi-Fi AP’s
  •  19 Telephone

Site hand over  2019

Practical completion  2019

 

1 of 5 completedTasks

  • Estimates & Quotations
  • Site handover
  • Installation
  • Practical completion
  • Project works completion

9. Complete 0% Tasks 0 / 0

0%
Description

10. FIDC008/2018VTC - Relocation of main entrance of the Vaal Campus Complete 100% Tasks 5 / 5

100%
Description

Relocate of main gate on Vaal campus

  •  9 Network Points
  •  0 Wi-Fi AP’s
  •  2 Telephone

Practical completion  27 Aug 2019

5 of 5 completedTasks

  • Estimates & Quotations
  • Site handover
  • Installation
  • Practical completion
  • Project works completion

11. FIDC007/2019VTC - Upgrade Lab for Natural Sciences Building A9-G03 ,Building 11A - G06 & G07 Complete 0% Tasks 0 / 5

0%
Description
  •  3 Network Points
  •  0 Wi-Fi AP’s
  •  3 Telephone

0 of 5 completedTasks

  • Estimates & Quotations
  • Site handover
  • Installation
  • Practical completion
  • Project works completion

12. FIDC002-2019VTC Faranani opgradeering Complete 20% Tasks 1 / 5

20%
Description

Upgrading Block A-C

  •  461 Network Points
  •  120 Wi-Fi AP’s
  •  3 Telephone

Site hand over    TBD    2019

Practical completion      TBD   2019

1 of 5 completedTasks

  • Estimates & Quotations
  • Site handover
  • Installation
  • Practical completion
  • Project works completion

13. CFIDC 021 2019 PC Refurbishment of Student Accounts and Bursaries Complete 46% Tasks 2 / 5

46%
Description

Upgrading F1 G54

  •  17  Network Points
  •   Wi-Fi AP’s
  •   17 Telephone

Site hand over   5 Aug  2019

Practical completion     22 Nov  2019

2 of 5 completedTasks

  • Estimates & Quotations
  • Site handover
  • Installation
  • Practical completion
  • Project works completion

14. FIDC 031/2018 PC Macro Maintenance of Vergeet-my-Nie Ladies Residence Complete 46% Tasks 2 / 5

46%
Description

Upgrading J11 Vergeet my nie

  •  137  Network Points
  •   98 Wi-Fi AP’s
  •   17 Telephone

Site hand over   29 April  2019

Practical completion     27  Nov  2019

2 of 5 completedTasks

  • Estimates & Quotations
  • Site handover
  • Installation
  • Practical completion
  • Project works completion

15. Complete 0% Tasks 0 / 0

0%
Description

16. Complete 0% Tasks 0 / 0

0%
Description

17. Complete 0% Tasks 0 / 0

0%
Description

18. Complete 0% Tasks 0 / 0

0%
Description

19. Complete 0% Tasks 0 / 0

0%
Description

20. Complete 0% Tasks 0 / 0

0%
Description

21. Complete 0% Tasks 0 / 0

0%
Description

22. Complete 0% Tasks 0 / 0

0%
Description

23. Complete 0% Tasks 0 / 0

0%
Description

24. Complete 0% Tasks 0 / 0

0%
Description

25. Complete 0% Tasks 0 / 0

0%
Description