JBOSS/JDK upgrade project

Project Description

The request was already listed as priority no 9 on the Project Prioritisation list.  It was re-initiated by Mari Prinsloo on 12 March 2019.

JDK is out of support and it is a risk.

Documents

No documents at this time.

Project Progress

65%

Project Timing

  • Start
    Mar 12 2019
  • End
    Jun 26 2020

03/12/2019 06/26/2020

100%

Overall Project Completion

  • 20%
  • 60%

65%

  • 40%
  • 80%

1. VSS Complete 100% Tasks 0 / 0

100%
Description

2. Vaadin Apps Complete 100% Tasks 0 / 0

100%
Description

3. JBPM Complete 0% Tasks 0 / 0

0%
Description

4. Pontoon Apps Complete 50% Tasks 0 / 0

50%
Description
  • BSUP
  • COI

Project Discussion 2 Responses to JBOSS/JDK upgrade project

  1. VSS code changes done and deployments received for testing.

    September 3, 2019 at 12:51 pm
    DASSIE JANSE VAN VUUREN
  2. Pontoon apps are scheduled to be updated in 2020

    July 29, 2019 at 9:30 am
    CHANDRÉ BOTHA