Move VV and VSS from F-drive (OI & BSS)

Project Description

Request was initiated by Hannes Kriel

We need to move the current deployments, client config files and dll files from the F drive to a separate storage for the VV and VSS environments. This has to be done because of Novel file sharing that is going to be decommissioned

Documents

Project Progress

90%

Project Timing

  • Start
    Jan 25 2016
  • End
    Mar 30 2020

01/25/2016 03/30/2020

100%

Overall Project Completion

  • 20%
  • 60%

90%

  • 40%
  • 80%

1. Make inventory of which files must move to the new storage Complete 100% Tasks 0 / 0

100%
Description

2. Draw up action plan on what can be moved first Complete 50% Tasks 0 / 0

50%
Description

3. Move test environments to new storage and start testing Complete 30% Tasks 0 / 0

30%
Description

4. Move prod environments to new storage and monitor Complete 0% Tasks 0 / 0

0%
Description

Project Discussion 8 Responses to Move VV and VSS from F-drive (OI & BSS)

  1. We will tackle this in March 2020. I would like to attach the list of items outstanding early in March.

    February 24, 2020 at 9:18 am
    RIAAN MARX
  2. We will tackle this beginning Feb and with approval in terms of priorities with Management. We had meeting with AOS and we are looking at 3 aspects: VV, VSS and Word Templates. We have sorted VV, need to test VSS on new drive and are engaging with Gerda to move templates to a public-type shared drive on nextcloud.

    January 22, 2020 at 3:01 pm
    RIAAN MARX
  3. Attending to this and try to complete by end Oct

    September 10, 2019 at 10:23 am
    RIAAN MARX
  4. On hold.

    September 10, 2019 at 10:07 am
    RIAAN MARX
  5. Ons gaan einde Mei die weer update en voor einde Junie 2019 afhandel. Dankie

    May 20, 2019 at 12:42 pm
    RIAAN MARX
  6. Martin is in final stage to test and move the storage

    January 7, 2019 at 9:49 am
    RIAAN MARX
  7. Waiting for resources. Project should be reviewed as it can be included in Jenkins project.

    April 18, 2016 at 11:05 am
    IAN CONRADIE
  8. Project scope can be determined: Only Business Systems. Project Manager should consult and collaborate with the Architecture and the relevant BSS staff.

    September 22, 2015 at 9:21 am
    YVETTE LABUSCHAGNE