NAC POD’S upgrade on NWU

Project Description

The current Bradford-NAC environment will be upgraded with a new operating system, Firmware and hardware resource infrastructure, which entails 7 x new PODS on PCM, 4 x in Vaal and Mafikeng campuses.

Documents

Project Progress

67%

Project Timing

  • Start
    Sep 26 2016
  • End
    Jul 30 2017

09/26/2016 07/30/2017

100%

Overall Project Completion

  • 20%
  • 60%

67%

  • 40%
  • 80%

1. Hardware Resource Request (Memory, Harddrive, CPU) Complete 100% Tasks 0 / 0

100%
Description

2. Download NAC Software for Instalation on PODS Complete 100% Tasks 0 / 0

100%
Description

3. Create and Install PODS on VM and install Software Complete 100% Tasks 0 / 0

100%
Description

4. PODS Creation on VM Complete 100% Tasks 3 / 3

100%
Description

3 of 3 completedTasks

  • PCM x 7
  • MFK x 4
  • VDK x 4

5. Schedule downtime and Maintenance + Communication to Campusses Complete 100% Tasks 3 / 3

100%
Description

3 of 3 completedTasks

  • PCM
  • VDK
  • MFK

6. Settings and Data transfer to new PODS Complete 100% Tasks 3 / 3

100%
Description

3 of 3 completedTasks

  • Transfer Network Segments
  • ACL's of Remediation
  • Setup Profiling of nodes

7. Test remediation in new envoronment Complete 100% Tasks 3 / 3

100%
Description

3 of 3 completedTasks

  • PCM
  • MFK
  • VDK

8. Testing of Profiling and scan in new environment Complete 100% Tasks 3 / 3

100%
Description

3 of 3 completedTasks

  • PCM
  • MFK
  • VDK

9. Transfer of Segments to new WI-Fi PODS Complete 100% Tasks 3 / 3

100%
Description

3 of 3 completedTasks

  • PCM
  • MFK
  • VDK