PC Lab Virtualization Project

Project Description

Cloud computing is the delivery of shared computing resources, software, or data as a service through the internet.

The goal of this project is to provide virtual desktops to any device and place and time, giving end users access to full university resources previously on accesible form university network connected lab PC’s

Work smarter not harder, to bring down lab managment overhead and staff resources needed to manage the enviroment.

Providing a secure space for online exam deliver on BYOD devices.

Documents

No documents at this time.

Project Progress

0%

Project Timing

  • Start
    Nov 01 2018
  • End
    Nov 30 2019

11/01/2018 11/30/2019

100%

Overall Project Completion

  • 20%
  • 60%

0%

  • 40%
  • 80%

1. Hardware Procurement and Provisioning Complete 100% Tasks 0 / 0

100%
Description

Infrastructure to procure VSAN and provision it.

DHET grant funded project

2. System Level Provisioning Complete 50% Tasks 0 / 0

50%
Description

Delivery of 7 Windows 2016 R2 servers where on the application level will run.

24 Feb 2020 Update:

Likely 7 new servers to be created for new deployment of application during week of 2 – 6 March 2020.

3. Application Level Provisioning Complete 10% Tasks 0 / 0

10%
Description

24 Feb 2020 Update:

 New Master Virtual Desktop Infrastructure (VDI) to be created during week of 2 – 6 March 2020

4. Testing Complete 0% Tasks 0 / 0

0%
Description

24 Feb 2020 Update:

Testing to be done during week 9 – 13 March 2020 after updating VMs with new Master in collaboration with Engineering and Computer Science

5. Implementation Roll Out For General Use Complete 0% Tasks 0 / 0

0%
Description

24 Feb 2020 Update:

Roll out to be done after testing

Project Discussion One Response to PC Lab Virtualization Project

  1. The project has been revived and there are weekly sessions by the project team. During the week of 24 February a project plan will be created in order to stick to the deadline of the coming exam. During the week of 2-6 March a consultant will be on site to assist with the re-creation of the environment (to spec) and to up-skill the relevant staff who will support various aspects of the system.