The request was initiated by Mari Prinsloo on  20 Sept 2018.

HR Support Project – Managed by Dassie J V Vuuren (oversee) & Lizwi Njani  (Development & implementation) in collaboration with Roald van den Berg (P&C – requirements alignment & implementation)

 

Documents

No documents at this time.

Project Progress

100%

Overall Project Completion

  • 20%
  • 60%

100%

  • 40%
  • 80%

1. Analysis and consolidation Complete 100% Tasks 4 / 4

100%
Description

4 of 4 completedTasks

  • List reports
  • Analysis of reports
  • Requirement analysis
  • Consolidation

2. Development Complete 100% Tasks 3 / 3

100%
Description

APEX Setup with Philip du Plooy and Riaan Marx

3 of 3 completedTasks

  • Setting up of Apex
  • Development of Apex reports
  • Development of formal reports

3. UAT Complete 100% Tasks 2 / 2

100%
Description

2 of 2 completedTasks

  • Apex reports
  • Formal Reports

4. Roll out and change management Complete 100% Tasks 2 / 2

100%
Description

Roll out to SMC November 2020

2 of 2 completedTasks

  • Apex reports
  • Formal reports

Project Discussion 4 Responses to P&C reporting optimisation (APEX)

  1. Dashboard available for SMC members from November 2020. Planned roll out to OE Heads 3 March

    February 24, 2020 at 9:31 am
    DASSIE JANSE VAN VUUREN
  2. Project proceeded with Johann Olivier doing the technical setup together with RedEdge. CAS authentication done and in production – demo held for Dr Mala. First phase of reports for Executive Management completed and to be rolled out week of 9 September

    September 3, 2019 at 8:45 am
    DASSIE JANSE VAN VUUREN
  3. Roald will not be part of the IT project team – BSS still need to determine the IT team – Usergroup will be ROald van den Berg, Nadia Botha and CLement Lerefolo

    January 8, 2019 at 12:22 pm
    DASSIE JANSE VAN VUUREN
  4. 02 Oct 2018: The project request was approved

    October 2, 2018 at 3:12 pm
    YVETTE LABUSCHAGNE

Leave a Reply