Vaal: Postgraduate Lab Building 13

Project Description

The request was initiated by Motlokwe Thobejane on 20 February 2019

Documents

Project Progress

51%

Project Timing

  • Start
    Feb 20 2019
  • End
    Sep 30 2020

02/20/2019 09/30/2020

98%

Overall Project Completion

  • 20%
  • 60%

51%

  • 40%
  • 80%

Project Discussion 3 Responses to Vaal: Postgraduate Lab Building 13

  1. With the Covid-19 delay and students not using this lab this has been postponed until end Spetember 2020

    August 17, 2020 at 9:32 am
  2. Points in Bib toned out and moved. Need to implement the new lab segment on switches and routers. Planning with Arc

    February 21, 2020 at 1:42 pm
  3. A meeting was held with Motlokwe, Oupa, Robert, Stefan and Flip to discuss the project request on the 15th of August 2019
    There are 30 PC’s that needs to be moved to the Lab segment.
    Oupa will go and tone the points & also check if the points terminates on its own switch.

    September 2, 2019 at 12:04 pm
    FLIP VAN SCHALKWYK