Project Description

Situation/Problem/Opportunity:

It has been identified that the VMWare Architecture needs to be revised in terms of how the disk subsystems have been exposed and allocated. Production systems are affected by TEST/DEV systems and IO has become a major factor in maintaining a stable and predictable environment. The result is that production systems are suffering performance issues, and are becoming unstable. The administration involved in configuring networking requirements and the exposure of disk subsystems, has also become a cumbersome process and also needs to be addressed.

Purpose Statement (Goals):

After a technical discussion and consultation from a VMWare expert, the following has been identified as key to addressing the problem. Split Production systems from TEST and DEV in terms of IO’s. Simplify how Networking and Disk exposure is configured, to minimize the complexity of administration actions. Implement and setup of QoS on the 3PAR

 

Project Progress

36%

Project Timing

  • Start
    Jun 01 2015
  • End
    Jun 30 2016

06/01/2015 06/30/2016

100%

Overall Project Completion

  • 20%
  • 60%

36%

  • 40%
  • 80%

1. Classify all services and systems. Distinguish between TEST/DEV and Prod Systems Complete 100% Tasks 1 / 1

100%
Description

1 of 1 completedTasks

  • Document current VMware Environment

2. Build a separate high performance VSA allocated to the Oracle ESX 5 node Cluster for the Oracle TEST/DEV environments Complete 50% Tasks 0 / 1

50%
Description

0 of 1 completedTasks

  • Tier 1.5 HIgh Performance Storage

3. Move all Oracle TEST/DEV environments to the new VSA Storage on the Oracle ESX cluster Complete 0% Tasks 0 / 0

0%
Description

4. Setup of a Tender process for VMWare Licenses for the new Oracle ESX Cluster Complete 0% Tasks 0 / 0

0%
Description

5. Simplify Disk Exposure by splitting Prod, Dev, and Test environments Complete 0% Tasks 0 / 0

0%
Description

6. Simplify Networking configuration by splitting Prod, Dev, and Test environments Complete 0% Tasks 0 / 0

0%
Description

7. Implement QoS on the 3PAR for Productions Systems Complete 0% Tasks 0 / 0

0%
Description

8. Build 5 Node Oracle ESX Cluster Complete 50% Tasks 1 / 2

50%
Description

1 of 2 completedTasks

  • Build 5 Node Cluster
  • Add storage to move Oracle Test Environments

9. Existing 3 PAR Disk Expansion Complete 100% Tasks 2 / 2

100%
Description

2 of 2 completedTasks

  • Update Firmware
  • Add extra disks

10. Commision new 3 PAR Complete 25% Tasks 1 / 4

25%
Description

1 of 4 completedTasks

  • Create Storage for Replication
  • Create Storage for HA/DR
  • Install Physical Hardware
  • Install FOE Switches

11. Upgrade VMWare PCM Complete 19% Tasks 1 / 10

19%
Description

1 of 10 completedTasks

  • Upgrade Toets Host van 5 na 6
  • Obtain HA/DR Cluster License
  • Upgrade Cluster 3 and Rebrand as Test/Dev Cluster
  • Decommission Cluster 1
  • Upgrade Cluster 4 and Rebrand as Infrastructure Cluster
  • Upgrade Cluster 2 and Rebrand as Novell P Drive Custer
  • Upgrade Cluster 5 and Rebrand as Oracle Cluster
  • Build HA/DR Cluster
  • Build Production Cluster
  • Add new 3PAR Storage to VMWare Clusters

12. VDK Upgrade Cluster01 and Rebrand as Production Cluster Complete 0% Tasks 0 / 0

0%
Description

13. MFK Upgrade Cluster and Rebrand as Production Cluster Complete 100% Tasks 2 / 2

100%
Description

2 of 2 completedTasks

  • Upgrade VCentre
  • Upgrade ESX Hosts

14. Install and Configure VEEAM Environment Complete 34% Tasks 1 / 3

34%
Description

1 of 3 completedTasks

  • PCM
  • VDK
  • MFK

15. Network Infrastructure Environment Complete 97% Tasks 2 / 5

97%
Description

2 of 5 completedTasks

  • Tier 2 Old Cluster Decommission (Move to New T2 Storage Cluster)
  • EVA Storage Move to Tier 1 Storage Cluster
  • ISCSI Backbone Revamp
  • Installation Blade Infrastructure
  • Server Backbone Upgrade

16. Split Production and Test Environments Complete 0% Tasks 0 / 0

0%
Description

Project Discussion One Response to VM Architecture refresh

  1. DR VMWare Execution Plan uploaded

    February 10, 2016 at 8:07 am
    HANNES KRIEL

Leave a Reply